Friday, May 25, 2012

Rehabilitation of 10 miles of Stevens Canyon Road Planned in 2012 and 2013 Phase 2 Effort

Mount Rainier National Park Superintendent Randy King and Federal Highway Administration, Western Federal Lands Highway Division officials announce that Phase 2 of the planned rehabilitation of 10 miles of Stevens Canyon Road was awarded to Tucci and Sons, Inc. of Tacoma, WA for $8,910,093.23 with a Notice to Proceed issued for project start on May 29, 2012 and a contract completion date of September 17, 2013. 
 
The National Park Service prepared an Environmental Assessment and a Finding of No Significant Impact (FONSI), which was approved by the Pacific West Regional Director on July 1, 2010.  The FONSI calls for the resurfacing, restoration, and rehabilitation of the Stevens Canyon Road and other related facilities, including bridges, tunnels, culverts, guard walls, retaining walls, turnouts and the short Wonderland Trail section adjacent to Reflection Lake. The improvements will occur along two segments of the road, totaling 10.09 miles of the 19 mile road. 

Starting in early June until September 4th, visitors should anticipate 20-minute delays, Monday – Friday, through each of two segments of roadwork on Stevens Canyon Road.

From September 4, 2012 until winter closure, Stevens Canyon Road will be closed to through traffic (for both vehicles and bicycles)  from just east of the intersection with the Paradise Valley Road to the east end of the tunnel at Box Canyon.

Visitors will be able to access Backbone Ridge, Box Canyon and adjacent trailheads via the East Entrance near State Route 123 during the 2012 closure. Wonderland Trail hikers as well as day hikers will be permitted to hike through the construction zone to access adjacent trails.

Forty-five sites have been identified as needing subsurface stabilization to halt roadway embankment creep that has resulted in surface tension cracks and appreciable horizontal and vertical displacement. Two sites require full roadway embankment replacement down to 22 foot depth and retaining/guard wall replacements.  Most of the sites require either ¾- width or full road embankment replacement down to 5 foot depth, some of which also require retaining/guard wall replacements, were stabilized during Phase 1 work completed in late October 2011. The contractor will also be repairing the tunnel walls at milepost 6.9 and 8.5 during the closure period. 

Stevens Canyon roadwork is scheduled to extend until mid September 2013, although no closures are anticipated during the 2013 season.


During the 2013 season, the contractor will focus on drainage improvements, repair/stabilization and reconstruction of historic rock retaining walls, milling/recycling the asphalt surface as road base; and resurfacing with new hot-mix asphalt which will be accomplished while the roadway is open to the public. At this time visitors should again anticipate maximum 20 minute delays through each segment Mondays through Fridays until project completion on September 17, 2013.  No closures are anticipated in 2013.

Stevens Canyon Road connects the east and west side of the park, extending for 19 miles from SR 123 at the east end to intersection with the Nisqually to Paradise Road at the west end, two miles south of Paradise. During the 2012 closure period, visitors are encouraged to access the Paradise area from the southwest via the Nisqually Entrance at east end of SR 706.  Visitors traveling from the east via SR 410, SR 123, and/or US 12 who wish to visit the Paradise area are encouraged to seek alternate routes.

While the construction and associated closures and traffic delays present an inconvenience, the rehabilitation work will not only improve the driving surface of the roadway, but ensure its longevity.

Updated information on this project may be obtained by calling Mount Rainier National Park at 360-569-2166. Information on this project, as well as general park information, is also available on Mount Rainier National Park’s website www.nps.gov/mora/parknews/newsreleases.htm.

###

NOTE:  Drivers can now get real time traffic and weather information by dialing 5-1-1 from most cell phones. This new traveler information system builds upon the highly successful Washington State Highway hotline that manages 4.6 million calls each year. Plan to call prior driving to the park, as cell phone coverage is minimal within the park. Callers can also use 5-1-1 to get statewide construction, mountain pass conditions, and state ferry system information, as well as toll free numbers for passenger rail and airlines. TTY users can call 1-800-833-6388.

Friday, May 11, 2012

MOUNT RAINIER SPRING/SUMMER OPENING SCHEDULE

With warmer, sunny days becoming a little more frequent in the Northwest now, it seems Spring has officially arrived and Summer is not far behind.  However, at Mount Rainier snow still blankets the slopes (15 feet at Paradise) and roadways.  The Spring melt is beginning and park Road Crews are cutting their way through the snowed-in roadway at Stevens Canyon.  This is still a great time of year to visit the park, to view the amazing snowpack, to cross-country ski or snowshoe.  Be sure to check on conditions with park staff before going – spring avalanches can be deadly.

Paradise Inn Opens May 18 - On Friday, May 18, the historic Paradise Inn opens its doors to welcome visitors for the 2012 season.  Constructed in 1916, the Inn showcases a beautiful lobby and dining room featuring hand painted hanging lamps depicting park wildflowers, three huge stone fireplaces to welcome guests, 118 guest rooms, a cafĂ©, and gift shop with authentic Native American arts and crafts.  A full service dining room offers Northwest cuisine.  The Inn is listed as a National Historic Landmark.

In addition to the Paradise Inn, the National Park Inn at Longmire is also open for visitors.  The National Park Inn offers 25 guests rooms, a cozy fireside room for guests to enjoy, full service restaurant, general store and gift shop.

Both inns are operated by Mount Rainier Guest Services, Incorporated. Reservations can be made on line at www.mtrainierguestservices.com  or by telephone at 360-569-2275.

Businesses in the gateway communities surrounding the park are also open daily providing lodging, meals, gifts, equipment rentals, horseback riding, fishing, special events and a variety of other needs to park visitors. Information on these businesses is available on the internet at
www.visitrainier.com, www.mt-rainier.com, www.staycrystal.com,
www.destinationpackwood.com or www.minerallake.com.


CURRENT STATUS AND PROJECTED OPENING DATES:
Note:  These dates are projected and may be subject to change depending on conditions.

ROADS:

  •   Stevens Canyon Road                                 May 25 @ 8:00 a.m.
  •   SR 410 to SR 123 over Cayuse Pass            Open
  •   White River Road to Campground lot         May 25
  •   Sunrise Road                                               June 22 @ 8:00 a.m.
  •   Mowich Lake Road                                     June 29 @ 8:00 a.m.
  •   Skate Creek Road (USFS Road 52)            Open
  •   Chinook Pass                                               May 25
  •   Westside Road                                             Open to Dry Creek

Road Construction:

Stevens Canyon Road:  Road construction repair work will be occurring on two sections of the Stevens Canyon Road throughout the summer.  Work will be Monday through Friday until Labor Day - 20-minute delays should be anticipated at each section.  After Labor Day the road will be closed to all traffic from just east of the intersection with the Paradise Valley Road to east end of the tunnel at Box Canyon for the remainder of the season,  Visitors will still be able to access Box Canyon via the East Entrance.  During closure period, the road will be closed to through traffic for both vehicles and cyclists.

SR 123:  A micro-surfacing  treatment will be applied on the roadway from MP 6.8 to MP 13.8 (Cayuse Pass) from August 6 to August 17, 2012 with 20-minute delays anticipated.    In addition, replacement of a failed deep culvert at MP 10.6 will take place in mid- to late September.  It is anticipated that the work will take 2-days to accomplish and due to the depth of the culvert a road closure will be necessary.  A press release will be issued prior to the closure.

Longmire:
Longmire Museum:  Open daily - 9:00 a.m.-4:30 p.m. through June 30.  9:00 a.m. -5:00 p.m. July 1-September 3
Longmire Wilderness Information Center:  Open daily -7:30 a.m. - 5:00 p.m.
National Park Inn: Open daily year round

Cougar Rock:
Cougar Rock Campground:  May 25
Cougar Rock Picnic Area:  May 25

Paradise:
Henry M. Jackson Visitor Center:  Open daily -10:00 a.m.-5:00 p.m. (until May 17)
Paradise Inn:  May 18 to June 15 -10:00 a.m.-6:00 p.m.
                       June 16 to September 2 – 10:00 a.m.-7:00 p.m.

Ohanapecosh:
Ohanapecosh Campground                    May 25
Ohanapecosh Visitor Center                  May 25–May 28 -10 a.m.-5 p.m. (Fri.,
                                                               Sat. Sun., Mon.)
                                                               June 2-3 (Sat., Sun.)
                                                               June 9-September 2 – 9:00 a.m.-6:00 p.m.

White River:
White River Road to Campground lot            May 25
White River Campground                               June 29

Sunrise:
Sunrise Lodge (snack bar & gift shop)         June 29
Sunrise Visitor Center                                  June 29

Carbon River:
Ranger Station                              Open year round - Call for hours -
360-829-9639


For additional information visit the park’s website at www.nps.gov/mora or call 360-569-2211. "You can connect to Mount Rainier National Park through our social media pages. Join the Mount Rainier community on Facebook, find out breaking news and road status updates through Mount Rainier's Twitter feed, explore the park and behind-the-scenes operations with our videos on YouTube, and share you own photos of Mount Rainier with other visitors in the Mount Rainier Flickr group."

Thursday, April 19, 2012

CELEBRATE NATIONAL PARK WEEK – Come Visit Mount Rainier for Free!

Mount Rainier National Park Superintendent Randy King advises that April 21– 29 is designated as National Park Week across the nation.  In celebration of this week, the Secretary of the Interior has announced that admission to all National Parks will be free during that time.

The theme for the week is “Picture Yourself in a National Park”, so bring your cameras and make photo memories of your visit to Mount Rainier with over 17 feet of snow on the ground at Paradise. About 10 inches is on the ground at Longmire.  The snow play (sledding) area at Paradise has closed for the season and the ranger-led snow shoe walks have concluded. Cross-country skiing and snowshoeing are still very popular activities during the Spring season.  Check with Rangers for current weather and avalanche conditions before heading out on your trip.

While many of the areas and roads at Mount Rainier still remain under winter snows, the southwest area of the park (State Route 706), including Longmire and Paradise is open.

The Henry M. Jackson Visitor Center at Paradise will be open daily during this period, offering visitor information, food service and gift shop.  A special Junior Ranger program will be given on Saturday, April 21 from 12:00 p.m. to 4:00 p.m. at the visitor center.

The National Park Inn at Longmire is open year round providing overnight accommodations, dining and a gift shop – a great place for a getaway in early Spring.  The Carbon River area is currently snow free and provides a great opportunity for hikers and bicyclists.

The road from Longmire to Paradise is closed nightly at Longmire and reopens each day after the roads have been plowed and maintained.  If unusually heavy snowfall occurs or other conditions are present making the road unsafe, it may be closed to the public at any time.  Through April 30 park visitors must carry tire chains in their vehicles when traveling on park roads as Spring weather in the mountains is very unpredictable and sudden snow storms may necessitate chains for safe travel.

Local businesses in the gateway communities surrounding the park are also open and ready for the beginning of the 2012 visitor season.  For more information visit these websites:  www.visitrainier.com, www.mt-rainier.com, www.staycrystal.com, www.destinationpackwood.com,  www.minerallake.com, or www.mtrainierguestservices.com

The Skate Creek Road (Forest Service Road 52) which travels along the park’s southeastern boundary east of Ashford to Packwood is expected to open to the public on Friday, April 27.

"You can connect to Mount Rainier National Park through our social media pages. Join the Mount Rainier community on Facebook, find out breaking news and road status updates through Mount Rainier's Twitter feed, explore the park and behind-the-scenes operations with our videos on YouTube, and share you own photos of Mount Rainier with other visitors in the Mount Rainier Flickr group."

Monday, January 23, 2012

Temporary Road Closure, Mt. Rainier National Park.

Press Relase:

The park road from Longmire to Paradise will remain closed to the public
today, January 23.  This is due to expanded air operations in the Paradise
area related to the ongoing search for four hikers/climbers who have been
missing for over a week. Weather conditions today are conducive to
conducting this aerial search, but this window of opportunity will likely
not last beyond today.  All available park and local resources are being
used to focus on this search.

Donna Rahier - Superintendent's Office
Mount Rainier National Park
360-569-6501
donna_rahier@nps.gov

Monday, December 12, 2011

Cascade foxes in Mt. Rainier National Park

Fox Research

Mount Rainier National Park has just begun a research project to assess
visitor impacts on Cascade foxes (Vulpes vulpes cascadensis). The Cascade
fox is a rare species currently known to inhabit only Mount Rainier and
Mount Adams.  Many of Mount Rainier’s Cascade foxes have learned to get
food from people, “begging” on roadways in the Paradise area, increasing
the risk to both foxes and humans.  The research will evaluate the
ecological impacts on these foxes as a result of human activities, and will
enable park managers to better manage visitor use and protect the foxes.
The study is a cooperative effort between Mount Rainier and the
USGS-Forestry and Rangeland Ecosystem Science Center.

Visitors may see radio collars on some foxes.  These radio collars
automatically collect time and location information via GPS receivers,
similar to what is used in a car or on the trails.  Programmed to record
time and location at 3.5 hour intervals, the collars will provide a wealth
of information of how visitor use may alter the natural movements and
habits of foxes.

Mount Rainier has had a persistent problem with people continually feeding
the foxes, and this project is designed to better evaluate the behavioral
responses of the foxes to this illegal and damaging practice.  The
substantial ongoing efforts to educate the public and enforce no-feeding
laws will continue.   Results of this study will lead researchers to better
understand human impacts and develop new ways of protecting the foxes and
keeping our wildlife wild.

For more information, contact Mason Reid, Wildlife Ecologist at Mount
Rainier National Park, at 360-569-6771.